News

Quality built into every detail
WROTE ABOUT US
OCT 27 2026
Quality built into every detail

Behind every detail on the Marina Dorćol construction site lies careful planning and coordination that future residents rarely see.

Read
WROTE ABOUT US
AUG 17 2026
A Blend of Industrial Heritage and Contemporary Architecture

The portal crane and pumping station in Dorćol are not being removed, they are becoming part of Marina Dorćol and its new public space, while the nearby power plant remains preserved.

Read
A Blend of Industrial Heritage and Contemporary Architecture
WROTE ABOUT US
AUG 14 2026
Heat Recovery Ventilation as a New Standard

The size of an apartment, its floor level and the view are not the only factors that define comfort. The quality of the air you breathe every day is equally important.

Read
Heat Recovery Ventilation as a New Standard
WROTE ABOUT US
JAN 06 2026
One of the core connections lies in respect and a forward-looking relationship with everything in your surroundings that you consider valuable.

Our lead architect, Stanislav Fiala, spoke with Forbes about contemporary architecture, his design approach, and the importance of a strong urban vision. During the interview, Fiala shared his perspectives on the transformation of urban spaces and the architectural challenges of today…

Read more at forbes.rs
One of the core connections lies in respect and a forward-looking relationship with everything in your surroundings that you consider valuable.
Load more

Construction update

At Building A, concreting of the third floor slab continued, and concreting of the fourth floor slab also began. At Building B, work continued on the concrete structure of the underground levels, ground floor and first floor. On both buildings, the concreting works covered the columns, walls and slabs of the respective levels. In October, brickwork also began at Building A.

At Building A, concreting of the first and second floor slabs was completed in September, marking the completion of the building’s podium structure, while concreting of the third floor slab began, with the building progressing toward the higher residential floors. At Building B, work continued on the concrete structure of the underground levels and ground floor slab, while concreting of the first floor slab also began. On both buildings, the concreting works covered the columns, walls and slabs of the respective levels.

During August, work at Building A continued with the concreting of the first and second floor slabs, while at Building B work continued on the concrete structure of the underground levels and the ground floor slab. On both buildings, the concreting works covered the columns, walls and slabs of the respective levels.

During July, work at Building A continued with the concreting of the ground floor slab and first floor slab. At Building B, work continued on the underground structures and ground floor slab.

During June, work at Building A involved the casting of the first and second floor slabs, as well as the vertical elements of the ground floor. At Building B, work continued on the foundation slab and the slab of level -1, where work on the walls and columns has also begun.

During May, work at Building A continued with the casting of the ground floor slab, as well as the walls and columns of the ground floor. Formwork and shuttering for the first floor slab also began. At Building B, work continued on the foundation slab and the walls of the second basement level, and the first intermediate floor slab of level -1 was cast. Work on the embankment was completed.

April brings progress across all key phases of construction at the Marina Dorćol. On Building A, vertical elements on Level -1, ground floor slabs and ground floor vertical elements have been completed — the structure is transitioning into its above-ground phase. On Building B, the foundation slab is advancing, completed to approximately 25–30%, with vertical elements beginning on the finished sections. Part of the excavation support along Dunavski Kej Street has been completed using retaining elements, while static load testing of the second pile has confirmed the quality of the deep foundation works.

During March, intensive construction progress continued on both buildings. On Building A, the foundation slab has been completed, while works have advanced to the ground floor slab and the construction of walls on level -1. On Building B (Talas Building), piling works have been completed, with geothermal system installation underway alongside foundation slab works. The first areas executed in stamped concrete have also been completed, which will become one of the distinctive features of the shared spaces within Marina Dorćol.

Works on the riverbank reinforcement have continued, while at Building A, following the concreting of the foundation slab and the walls on level -1, construction has been progressing intensively in the underground levels where the garages will be located. In parallel, work on geothermal probes has continued at Building B, and the concreting of the first section of the foundation slab has begun, representing an important step in the further stabilization of the building’s structure.

During January, works on the riverbank reinforcement continued, along with concrete works on Building A. Following the completion of part of the foundation slab, the casting of the first walls on level -1 began, marking further progress in the formation of the building’s underground structure. In parallel, works on the installation of probes and piles on Building B are entering the final phase.

During December, significant progress was achieved on the construction site. The first section of the foundation slab was completed on Building A, while works on pile and borehole construction continued with Building B. Progress on the riverbank reinforcement is increasingly visible, and all works are proceeding in line with the planned schedule.

The thousandth pile has been installed, and piling works on Building A have been completed. The first reinforced-concrete works on the riverbank retaining structure have been carried out, along with the continuation of works on the geothermal energy system.

Continuation of works on the underground levels of First Phase, and the start of the implementation of the geothermal heating and cooling system.

During September, works were carried out on the installation of steel sheet piles and the construction of concrete piles for the riverbank retaining structure, large-scale excavation, and the protection of foundation pits for Buildings A and B, as well as the construction of wells for groundwater pumping.

During August, works were carried out on the protection of the riverbank retaining structure, excavations for the underground levels, and the commencement of foundation pits.

After obtaining the building permit, works commenced on site clearing and preparations for the start of construction of the first phase.

Zakažite sastanak
Book an Appointment
  • Project
  • Location
  • Apartments
  • Interiors
  • VR presentation
  • Gallery
  • Architecture
  • Lifestyle & Amenities
  • Sales Pavilion
  • Contact

0800 80 80 85
info@marinadorcol.rs

More Information About the Developer

2026 Marina Dorćol. All rights reserved.
Cookie Policy Privacy Policy
  • Project
  • Location
  • Apartments
  • Interiors
  • FB
  • In
en
  • srb
News
Contact